A blowout preventer accumulator, also known as a BOP accumulator, is a critical component of the blowout preventer (BOP) system used in the oil and gas industry. It is designed to store and supply hydraulic fluid under pressure to operate the BOP components when needed during drilling and well control operations.

Purpose of BOP Accumulator:

The primary purpose of a BOP accumulator is to ensure the reliable and immediate activation of the blowout preventer in case of an emergency, such as a blowout or uncontrolled flow of hydrocarbons from the well. The BOP is a critical safety device that is used to shut off the wellbore and prevent the escape of formation fluids during drilling or completion operations.

The accumulator system provides hydraulic pressure to operate the various components of the BOP, such as the rams (blowout preventer elements that seal off the wellbore) and the annular preventer (a rubber element that can close around the drill pipe). This pressure allows the BOP to seal off the well and regain control of the wellbore if unexpected pressure surges occur during drilling.

Response Time For The BOP Accumulator Unit

The closing system should be capable of closing each ram preventer within 30 seconds. Closing time should not exceed 30 seconds for annular preventers smaller than 18 3/4 inches and 45 seconds for annular preventers 18 3/4 inches and larger.

Requirements for BOP Accumulator Unit Valves, Fittings, and Pressure Gauges

  • Multi-bottle accumulator banks should have valving for bank isolation. An isolation valve should have a rated working pressure at least equivalent to the designed working pressure of the system to which it is attached and must be in the open position except when accumulators are isolated for servicing, testing, or transporting. Accumulator bottles may be installed in banks of approximately 160 gallons capacity if desired, but with a minimum of two banks.
  • The necessary valves and fittings should be provided on each accumulator bank to allow a pressure gauge to be readily attached without having to remove all accumulator banks from service. An accurate pressure gauge for measuring the accumulator pre-charge pressure should be readily available for installation at any time.

Maintenance of BOP Accumulator:

Maintenance of the BOP accumulator is of utmost importance to ensure its proper functioning and reliability in critical situations. Here are some key aspects of BOP accumulator maintenance:

  1. Regular Inspections: The accumulator system should be inspected regularly to check for any signs of wear, leaks, or damage. Visual inspections and pressure tests are essential to identify potential issues.
  2. Fluid Quality: The hydraulic fluid used in the accumulator system should be of high quality and compatible with the BOP components. Regular fluid analysis and replacement are necessary to maintain proper fluid performance.
  3. Pressure Testing: Periodic pressure testing of the accumulator system is crucial to verify its ability to deliver the required pressure to operate the BOP. Pressure tests are typically carried out at specified intervals or after any maintenance activities.
  4. Preventative Maintenance: Regular maintenance and servicing of the accumulator, including cleaning and greasing of moving parts, should be performed as recommended by the manufacturer.
  5. Component Replacement: Worn or damaged components should be replaced promptly with genuine spare parts to ensure the accumulator’s integrity and performance.
  6. Training: Personnel involved in maintaining and operating the BOP accumulator should receive proper training to handle the equipment safely and effectively.

The BOP accumulator system is a critical safety component, and its proper maintenance and regular inspection are essential to ensure the reliability of the overall blowout preventer system and enhance well control capabilities during drilling operations.